|
The word "fun" and "earned value" are rarely, if ever, used together. The last time I heard about a "fun" math calculation was when my fifth grade teacher tried to motivate us to solve story problems. I never really cared to know when two trains, traveling toward each other at 20 meters per second and 6,000 meters apart, would collide. Okay. The answer is 2.5 minutes, but how does this apply to earned value? Determining a project's earned value is a story problem (without the colliding trains, although some projects fit this analogy): Joe is managing a small $35,905 J2EE software project that is planned to last 64 days. A recent review of the status report indicated the project had planned to spend $23,570 and had only completed $19,575 of work. The project spent $23,170 to complete the work to date. Answer the following questions: - If the project continues at this performance level, what will be the final cost of the project?
- Does the team need to increase or decrease its performance?
- How many days will it take to complete the project?
Initially, these questions make you feel like you're strapped to those two colliding trains, but with MS-Project you can calculate the answers in less than the 2.5 minutes it takes for the two trains to collide. The previous articles, How to Calculate EVA with MS-Project Part 1 and Part 2 , introduced MS-Project's Earned Value table. MS-Project also supports two other earned value tables that provide additional cost and schedule performance information. The Earned Value Cost Indicator and Earned Value Schedule Indicator tables automatically calculate the cost performance (CPI) and schedule performance (SPI) indices mentioned in the previous article. They also provide cost and schedule variances and provide a percent complete for the budget and the project schedule. To view either of these tables, perform the following steps: Start on the Gantt Chart View or click on an active window pane to change the underlying table Select View – Table – More Tables menu item. The More Tables dialog box will appear and you can select from a variety of tables. Select one of the following tables:Select the Earned Value Cost Indicators table for cost performance information; select the Earned Value Schedule Performance Indicators table for schedule performance information. Click OK.
The current earned value information will be displayed for each task. Figure 1 displays the Earned Value Cost Indicators table: 
Figure 1: Earned Value Cost Indicators Table Figure 2: Earned Value Schedule Indicators Table This article was written by Andy Makar and originally published at Gantthead.com
|